Update: Golden Glow Village Project 1
8 March 13, 2012 by admin · Filed under: Construction Update
HomeChoice Planners & Construction has been working for this project in Golden Glow Village for almost 7 months now. Within this almost 7months of work, a lot of things have done and a lot of developments can be seen. Last week, we were able to do the following activities:
-Ceiling works 55%
-Carpentry works 45%
–Tile works 95%
-Installation of wood tiles 100%
-Glass works 45%
-Roofing works 100%
-Installation of door jambs 100%
For this week’s developments, we were able to work on the following:
-Ceiling works 90%
-Painting works 50%
-Carpentry works 90%
–Grinding of wood tiles 100%
-Glass works 90%
–Fence works 50%
-Installation of partition at attic 90%
The lined-up activities for next week are as follows: continuation of Painting works, Carpentry works, Glass works, Electrical works and Fence works. This project is almost near to its completion and we just cannot wait to see the finish product of this project. We couldn’t thank enough the family who trusted us to realize their dream house. It is our great pleasure to serve them. As to the other accomplishments to this project, we’ll just keep you all posted!