“ From all the holiday seasons, comes the very enhanced works for the project.”
From the series of holiday seasons we had, and for the events we had in different establishments and organizations, we come to this result in the field we are in. This project we have in Kisanlu in Iponan area is now in motion to almost full blast. For months of having this project constructed; improvements are being visible this time. There are lots of construction developments done for this unit. To have those viewed, I have the following:
Installation of railings at stair
Installation of railings at terrace
Installation of ceiling in 100%
Installation of cabinets 70%
Tile works in 85%
Sanding of wood tiles in 90%
Tapping of stairs in 100%
These are the works done last week and for this week, here are the following:
Installation of railings at stair in 100%
Installation of railings at terrace in 100%
Installation of cabinets in 80%
Tile works in 90%
Glass works in 20%
For next week we are looking forward to have the following finished; the fence works, glass works, paintings, cabinet works, electrical works and for clearing. We will be finishing this project as much as possible soon with all the needed features done and tasks completed. We will update all of you with this project online and inviting you all as well of making this project as one of your inspirations to extend to us, as well, all of your house concern to be done and let us mold your dream house reachable!